Base concrete pad and bottom panel assembly of colex grp tank

Base Concrete PAD & Bottom Panel Assembly

Wall panel assembly of colex grp water tank

Wall Panel Asseambly

Internal tie-rod roof suport assembly of colex grp water tank

Internal Tie-Rod & Roof Support Assembly

Completely assembled colex grp water tank

Assembly Completed

Installation and Caution

  • Customers are requested to make foundation pad construction according to the designed specifications and the strength of the site.
  • Check the evenness of foundation (within 5mm) and the flatness of base material. (within 0.5mm)
  • Check rust of the external reinforced material and any bolts and nuts, their tightness.
  • check installed state of the external ladders and water level gauge.
  • check bending of the water tank wall panel(maximum up to 1% of water tank height) and check skewness of the water tank.
  • Check a corrosion inhibitor coating on the internal reinforced material and bolts tightness.